CASE STUDY

Southern Reliability Project

CASE STUDY

Southern Reliability Project

PUBLISHED October 10, 2024

CATEGORY Case Studies, Transmission

Case Study Image

Improved reliability and provided relief to congested electrical grid in Southern Illinois.

Start Date: 2020
End Date: 2023
Project Location: Southern Illinois

140-mile transmission project – complete rebuild. The existing 230kV line was composed of steel lattice towers and wood H-frame structures. The new 345kV line was built with direct embed steel poles backfilled with rock or concrete and structures on concrete foundations. The primary purpose of the project was to improve reliability and provide relief to a congested electrical grid. INTREN also performed ROW tree clearing.